Excavation of the Miraflores (Arcadia) Shopping Centre
Explore My Work
LEADING THE EXCAVATION TEAM OF THE SIX FLOORS UNDERGROUD OF A SHOPPING CENTRE
Responsibilities
-
Planning the excavation of 326000m3 in open sky in an area of 16000m2
-
Planning and execution of the different ways to increase daily excavation volumes in urban areas
-
3D design of the excavation and how it would be implemented
-
Coordinator of the entire area belonging to excavation
-
Plan and coordinate the daily volume of trucks double traction and verification of the environmental part by land movement issues.
Achievements:
-
It was possible to increase the daily volume excavated to 4300m3 in the maximum curve well above the expected average.
-
By increasing the daily volume excavated, it was possible to recover the time that had been lost in another part of the contract.
-
By having a coherent planning and strategically determined load sites, the load is optimized by reducing the loading time and waiting to increase the daily trips of each dump truck which results in a gain of time and money.